As reported on November 20, 2026, Ethereum developers had not decided whether to change the specifications for Glamsterdam, a planned hard fork intended to increase network capacity and efficiency. The decision turns on a compatibility risk: proposed gas-pricing changes could alter assumptions that existing smart contracts rely on.
What the reviews found
Blockchain security firm ChainSecurity warned in October that gas-repricing proposals EIP-8037 and EIP-8038 could disrupt existing contracts and potentially expose them to exploitation. Developers subsequently postponed the Hoodi testnet fork, which had been scheduled for October 26. Researchers identified 13 real-world examples of potentially affected contracts that month; a November investigation examined eight smart-contract invariants—properties expected to remain true—that the upgrade could disrupt.
At Thursday’s All Core Developers meeting, developers said the Ethereum Foundation, ChainSecurity and security firm Dedaub had collectively contacted at least 50 affected companies. Three projects were classified as high impact, with fixes completed or expected by mid-December. Medium-impact projects reported timelines extending to January 10.
The choice is not simply whether to fix known cases. Developers discussed retaining the existing specifications or modifying them to reduce compatibility risks, while acknowledging that a change protecting one set of contracts might disrupt another. One developer warned that every specification change could break invariants not yet identified.

Schedule remains conditional
Under the existing specifications, Glamsterdam could reach mainnet as early as mid-January 2027. Developers said waiting until January to decide could move activation to late February or early March; adopting modifications could push it to April or May. None of those dates was a confirmed activation date.
Developers also discussed narrowing the scope of the subsequent planned fork, Hegotá, to prioritize post-quantum cryptography. Some questioned whether a narrower scope would help without shortening the rollout. A preliminary review of EIP-8151, an account-migration protection proposal, identified a potentially large number of existing contracts that could be affected. No decision was reached on Hegotá’s scope; client teams were expected to submit their positions before further discussions in two weeks.