In a November 17, 2026 report, PANews cited CryptoSlate on a Sepolia simulation using the Juicebox V6 contract. Developers found four paths in which a transaction succeeded overall while an internal payment failed. In one example, a buyer retained an NFT but a payment intended for another project was skipped. In another, a user withdrew funds without the 2.5% fee being deducted.
The developers attributed the behavior to gas consumption during execution: under the Glamsterdam rules being tested, an internal payment that writes to new storage could run out of gas and fail before the outer transaction does. The reported result comes from a testnet simulation; the source does not establish that these paths have occurred on Ethereum mainnet.